- Launched
- Mar 20224 yrs originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 1 yr
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 82 of 12367% · 96 rehab units
- Buildings
- 10.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale82 booked out of 123 units
Rehab96 units for existing members
Total 219 units. Rehab units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 53
- 2 BHK
- 133
- 3 BHK
- 14
- Other units
- 16
- Total units
- 219
- Buildings
- 1
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 123
- Rehab units
- 96
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 99% | 82 | |
| 100% | 100% | 68% | 77 | |
| 100% | 92% | 8% | 61 | |
| 100% | 92% | 8% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400092
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs | 5 yrs 4 mths |
| Possession date extended | By 1 yr | 0 of 5 |
| Possession date (MahaRERA) | Mar 2027 | Dec 2027 |
| Concrete structure (RCC) | 100% | 91% |
| Units booked (free sale) | 67% | 80% |
| MahaRERA complaints (filed by or against the builder) | 0 | 1 |
The 5 projects
- Paradigm Anantaara, Borivali West
- Ipsit Anand Mangal, Borivali West
- Avyukta Neelkamal, Borivali West
- Khandelwal Luxor, Borivali West
- Khandelwal Reserve, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Paradigm Anantaara | April 2022 | December 2030 | 0% | 163 units booked out of total 208 units |
| Ipsit Anand Mangal | May 2022 | December 2027 | 100% | 82 units booked out of 103 units for sale |
| Avyukta Neelkamal | May 2022 | September 2026 | 100% | 46 units booked out of 63 units for sale |
| Khandelwal Luxor | June 2022 | Dec 2027 – Dec 2029 | 55% | 216 units booked out of 257 units for sale |
| Khandelwal Reserve | June 2022 | Dec 2027 – Dec 2029 | 91% | 210 units booked out of 262 units for sale |
About this project
Shivsagar by Gurukrupa Developers is a 219-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in March 2022 with possession due in March 2027. 82 units booked out of 123 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shivsagar is a BMC-sanctioned project by Gurukrupa Developers in Borivali West, Mumbai 400092, registered with MahaRERA as P51800034270. It was launched in March 2022. It has 219 units in 1 building: 203 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 219 units, 123 are for sale and 96 are rehab units for existing members.
Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
82 units booked out of 123 units for sale (67%). Since the July 2026 update, 5 more units have been booked.