Ipsit Anand Mangal, Borivali West

by Navkar Developers · Borivali West, Mumbai 400092 · Map

Launched
May 20225 yrs 7 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
82 of 10380% · 61 rehab units
Buildings
30.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale82 booked out of 103 units

Rehab61 units for existing members

Total 164 units. Rehab units are not for sale.

Project facts

1 RK
10
1 BHK
24
2 BHK
76
3 BHK
43
Other units
11
Total units
164
Buildings
3
Land
0.5 acres
Phases
1
MahaRERA complaints
1
Free-sale units
103
Rehab units
61

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 67%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 62%Dec 2025: Concrete structure (RCC) 41%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%82
100%100%0%80
67%41%0%–
100%62%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 7 mths4 yrs 10 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)Dec 2027Sep 2027
Concrete structure (RCC)100%96%
Units booked (free sale)80%79%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ipsit Anand Mangal by Navkar Developers is a 164-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in May 2022 with possession due in December 2027. 82 units booked out of 103 units for sale. The concrete structure (RCC) is complete.

Read full summary

Ipsit Anand Mangal is an SRA-sanctioned project by Navkar Developers in Borivali West, Mumbai 400092, registered with MahaRERA as P51800045322. It was launched in May 2022. It has 164 units in 3 buildings: 153 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 164 units, 103 are for sale and 61 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.

82 units booked out of 103 units for sale (80%). Since the July 2026 update, 2 more units have been booked.