Destiny One, Bhandup West
by Padmamala Developers · Bhandup West, Mumbai 400078 · Map
- Launched
- Apr 20223 yrs 8 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 2 yrs
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 74 of 74100% · 2 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale74 booked out of 74 units
Rehab2 units for existing members
Total 76 units. Rehab units are not for sale.
Project facts
- 1 RK
- 17
- 1 BHK
- 42
- 2 BHK
- 9
- Other units
- 8
- Total units
- 76
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 74
- Rehab units
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 74 | |
| 0% | 0% | 0% | 74 | |
| 0% | 0% | 0% | 74 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400078
Projects with 30–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 3 yrs 9 mths |
| Possession date extended | By 2 yrs | 2 of 5 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2026 |
| Concrete structure (RCC) | 100% | 83% |
| Units booked (free sale) | 100% | 41% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Shraddha Prime, Bhandup West
- Sarvodaya Pride, Bhandup West
- Om Sai Sra Chs Ltd, Bhandup West
- Dream Olympia, Bhandup West
- Rudani Pride Kailash Park F Plot A Wing, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shraddha Prime | March 2022 | December 2025 | 100% | 28 units booked out of total 114 units |
| Sarvodaya Pride | February 2022 | April 2027 | 83% | 64 units booked out of total 113 units |
| Om Sai Sra Chs Ltd | February 2022 | December 2024 | 100% | 38 units booked out of total 38 units |
| Dream Olympia | January 2022 | December 2026 | 30% | 21 units booked out of total 103 units |
| Rudani Pride Kailash Park F Plot A Wing | November 2022 | December 2027 | 0% | – |
About this project
Destiny One by Padmamala Developers is a 76-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in April 2022 with possession due in December 2027. 74 units booked out of 74 units for sale. The concrete structure (RCC) is complete.
Read full summary
Destiny One is an SRA-sanctioned project by Padmamala Developers in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800034629. It was launched in April 2022. It has 76 units in 1 building: 68 homes (1 RK, 1 BHK and 2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 76 units, 74 are for sale and 2 are rehab units for existing members.
Its registered possession date is December 2027, extended by 2 years from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes not started.
74 units booked out of 74 units for sale (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100%.