Sarvodaya Pride, Bhandup West
by Jyotiraditya Realtors And Developers LLP · Bhandup West, Mumbai 400078 · Map
- Launched
- Feb 20222 yrs 7 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 2 yrs 7 mths
- Concrete structure
- 83%Mid-construction
- Booked
- 64 of 11357% · 62 in Jul 2026
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 1
- 1 BHK
- 45
- Other units
- 67
- Total units
- 113
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 56
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 83% | 40% | 64 | |
| 100% | 0% | 0% | 62 | |
| 100% | 0% | 0% | 62 | |
| 100% | 0% | 0% | 5 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400078
Projects with 20–100 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 7 mths | 3 yrs 8 mths |
| Possession date extended | By 2 yrs 7 mths | 3 of 5 |
| Possession date (MahaRERA) | Apr 2027 | Jun 2026 |
| Concrete structure (RCC) | 83% | 100% |
| Units booked | 57% | 70% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Om Sai Sra Chs Ltd, Bhandup West
- Dream Olympia, Bhandup West
- Destiny One, Bhandup West
- Govind Solitaire, Bhandup West
- Kshitij Eminence, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Om Sai Sra Chs Ltd | February 2022 | December 2024 | 100% | 38 units booked out of total 38 units |
| Dream Olympia | January 2022 | December 2026 | 30% | 21 units booked out of total 103 units |
| Destiny One | April 2022 | December 2027 | 100% | 74 units booked out of 74 units for sale |
| Govind Solitaire | August 2021 | June 2026 | 90% | 13 units booked out of 30 units for sale |
| Kshitij Eminence | March 2021 | June 2026 | 100% | 38 units booked out of 54 units for sale |
About this project
Sarvodaya Pride by Jyotiraditya Realtors And Developers LLP is a 113-unit project in Bhandup West, Mumbai 400078, launched in February 2022 with possession due in April 2027. 64 units booked out of total 113 units. The concrete structure (RCC) is 83% complete.
Read full summary
Sarvodaya Pride is a project by Jyotiraditya Realtors And Developers LLP in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800033300. It was launched in February 2022. It has 113 units in 1 building: 46 homes (1 RK and 1 BHK) and 67 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 2 years 7 months from the original September 2024. Construction: excavation complete, structure (RCC) 83% complete, final finishes 40% complete.
64 units booked out of total 113 units (57%). Since the July 2026 update, 2 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 83% and the possession date has moved from December 2025 to April 2027.