- Launched
- Apr 20222 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr 9 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 98 of 10891% · 32 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale98 booked out of 108 units
Rehab32 units for existing members
Total 140 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 66
- 2 BHK
- 66
- Other units
- 8
- Total units
- 140
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 108
- Rehab units
- 32
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 98 | |
| 100% | 72% | 0% | 98 | |
| 100% | 72% | 0% | 98 | |
| 100% | 57% | 0% | 94 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400083
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 3 yrs 8 mths |
| Possession date extended | By 1 yr 9 mths | 3 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 91% | 98% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Sai Laxmi Residency, Vikhroli
- Omkaar Solitaire, Vikhroli
- The Rising 58, Vikhroli
- Shraddha Pleasant, Vikhroli
- Swastik Platinum, Vikhroli
- Adishakti Chs Adityaraj Prime, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sai Laxmi Residency | April 2022 | December 2026 | 39% | 140 units booked out of total 141 units |
| Omkaar Solitaire | April 2022 | December 2026 | 100% | 91 units booked out of 113 units for sale |
| The Rising 58 | April 2022 | December 2025 | 100% | 115 units booked out of 118 units for sale |
| Shraddha Pleasant | March 2022 | June 2027 | 100% | 122 units booked out of 122 units for sale |
| Swastik Platinum | May 2022 | December 2026 | 100% | 280 units booked out of total 280 units |
| Adishakti Chs Adityaraj Prime | June 2022 | March 2026 | 91% | 143 units booked out of total 152 units |
About this project
Opulent by Reki Developers LLP is a 140-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in April 2022 with possession due in December 2026. 98 units booked out of 108 units for sale. The concrete structure (RCC) is complete.
Read full summary
Opulent is a MHADA-sanctioned project by Reki Developers LLP in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800034812. It was launched in April 2022. It has 140 units in 1 building: 132 homes (1 and 2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 140 units, 108 are for sale and 32 are rehab units for existing members.
Its registered possession date is December 2026, extended by 1 year 9 months from the original March 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
98 units booked out of 108 units for sale (91%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 72% to 100% and the possession date has moved from September 2025 to December 2026.