Swastik Platinum, Vikhroli
Ready to move
by Suvasya Builders And Developers LLP · Vikhroli, Mumbai 400083 · Map
- Launched
- May 20224 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked
- 280 of 280100% · 244 in Jul 2026
- Buildings
- 30.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 99
- 2 BHK
- 138
- 3 BHK
- 36
- Other units
- 7
- Total units
- 280
- Buildings
- 3
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 280 | |
| 100% | 100% | 100% | 244 | |
| 100% | 91% | 0% | 244 | |
| 100% | 91% | 0% | 166 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400083
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 7 mths | 3 yrs 8 mths |
| Possession date extended | No | 3 of 6 |
| Possession date (MahaRERA) | Dec 2026 | Sep 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 100% | 92% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- The Rising 58, Vikhroli
- Adishakti Chs Adityaraj Prime, Vikhroli
- Omkaar Solitaire, Vikhroli
- Opulent, Vikhroli
- Sai Laxmi Residency, Vikhroli
- Central Park, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| The Rising 58 | April 2022 | December 2025 | 100% | 115 units booked out of 118 units for sale |
| Adishakti Chs Adityaraj Prime | June 2022 | March 2026 | 91% | 143 units booked out of total 152 units |
| Omkaar Solitaire | April 2022 | December 2026 | 100% | 91 units booked out of 113 units for sale |
| Opulent | April 2022 | December 2026 | 100% | 98 units booked out of 108 units for sale |
| Sai Laxmi Residency | April 2022 | December 2026 | 39% | 140 units booked out of total 141 units |
| Central Park | February 2022 | May 2026 | 100% | 214 units booked out of 237 units for sale |
About this project
Swastik Platinum by Suvasya Builders And Developers LLP is a 280-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in May 2022 with possession due in December 2026. 280 units booked out of total 280 units. The concrete structure (RCC) is complete.
Read full summary
Swastik Platinum is a MHADA-sanctioned project by Suvasya Builders And Developers LLP in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800045216. It was launched in May 2022. It has 280 units in 3 buildings: 273 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
280 units booked out of total 280 units (100%). Since the July 2026 update, 36 more units have been booked.