Unicorn Heights, Borivali West
by Teoama Infrastructure Private Limited · Borivali West, Mumbai 400092 · Map
- Launched
- Apr 20223 yrs 2 mths originally promised
- Possession (MahaRERA)
- Jun 2028Extended by 3 yrs
- Concrete structure
- 75%Mid-construction
- Booked
- 7 of 5712%
- Buildings
- 20.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 38
- 2 BHK
- 19
- Total units
- 57
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 0% | 7 | |
| 100% | 75% | 0% | 7 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 20–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 3 yrs 6 mths |
| Possession date extended | By 3 yrs | 3 of 6 |
| Possession date (MahaRERA) | Jun 2028 | Mar 2026 |
| Concrete structure (RCC) | 75% | 95% |
| Units booked | 12% | 82% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Anamika Niwas Chslltd, Borivali West
- Parul Kunj Chs Ltd, Borivali West
- Prathamesh Solitaire, Borivali West
- Om Vasudev Chs Ltd, Borivali West
- Sun Sumit Deepshal, Borivali West
- Shiv Tapasya, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Anamika Niwas Chslltd | April 2022 | March 2025 | 100% | 14 units booked out of 21 units for sale |
| Parul Kunj Chs Ltd | May 2022 | March 2026 | 100% | 42 units booked out of total 51 units |
| Prathamesh Solitaire | March 2022 | October 2027 | 77% | 45 units booked out of total 48 units |
| Om Vasudev Chs Ltd | May 2022 | March 2026 | 100% | 38 units booked out of total 42 units |
| Sun Sumit Deepshal | June 2022 | December 2026 | 0% | 36 units booked out of total 80 units |
| Shiv Tapasya | July 2021 | September 2025 | 90% | – |
About this project
Unicorn Heights by Teoama Infrastructure Private Limited is a 57-unit MHADA-sanctioned project in Borivali West, Mumbai 400092, launched in April 2022 with possession due in June 2028. 7 units booked out of total 57 units. The concrete structure (RCC) is 75% complete.
Read full summary
Unicorn Heights is a MHADA-sanctioned project by Teoama Infrastructure Private Limited in Borivali West, Mumbai 400092, registered with MahaRERA as P51800034960. It was launched in April 2022. It has 57 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2028, extended by 3 years from the original June 2025. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.
7 units booked out of total 57 units (12%).