Shiv Tapasya, Borivali West
Lapsed
by Jetbuild Developers Shiv Tapasya Project · Borivali West, Mumbai 400092 · Map
- Launched
- Jul 20212 yrs 11 mths originally promised
- Possession (MahaRERA)
- Sep 2025Extended by 1 yr 3 mthsWhat does Lapsed mean?
- Concrete structure
- 90%Mid-construction
- Booked
- –
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 21
- 2 BHK
- 37
- 3 BHK
- 8
- Other units
- 3
- Total units
- 69
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 90% | – | |
| 100% | 90% | 90% | – | |
| 100% | 90% | 90% | 43 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400092
Projects with 30–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 3 yrs 10 mths |
| Possession date extended | By 1 yr 3 mths | 1 of 3 |
| Possession date (MahaRERA) | Sep 2025 | Dec 2026 |
| Concrete structure (RCC) | 90% | 75% |
| Units booked | – | 45% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Unicorn Heights, Borivali West
- Parul Kunj Chs Ltd, Borivali West
- Sun Sumit Deepshal, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Unicorn Heights | April 2022 | June 2028 | 75% | 7 units booked out of total 57 units |
| Parul Kunj Chs Ltd | May 2022 | March 2026 | 100% | 42 units booked out of total 51 units |
| Sun Sumit Deepshal | June 2022 | December 2026 | 0% | 36 units booked out of total 80 units |
About this project
Shiv Tapasya by Jetbuild Developers Shiv Tapasya Project is a 69-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in July 2021; its MahaRERA registration has lapsed. The concrete structure (RCC) is 90% complete.
Read full summary
Shiv Tapasya is a BMC-sanctioned project by Jetbuild Developers Shiv Tapasya Project in Borivali West, Mumbai 400092, registered with MahaRERA as P51800029976. It was launched in July 2021. It has 69 units in 1 building: 66 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in September 2025, after an extension of 1 year 3 months from the original June 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes 90% complete.