Amey Apartments, Andheri East
Ready to moveLapsed
by Amey Realty And Construction LLP · Andheri East, Mumbai 400069 · Map
- Launched
- May 20223 yrs 7 mths originally promised
- Possession (MahaRERA)
- Oct 2026Extended by 10 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 49 of 6971%
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 53
- 3 BHK
- 16
- Total units
- 69
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 49 | |
| 100% | 100% | 100% | 49 | |
| 100% | 100% | 70% | 49 | |
| 100% | 50% | 0% | 10 |
"–" means MahaRERA shows no figure for that update.
About this project
Amey Apartments by Amey Realty And Construction LLP is a 69-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in May 2022; its MahaRERA registration has lapsed. 49 units booked out of total 69 units. The concrete structure (RCC) is complete.
Read full summary
Amey Apartments is a BMC-sanctioned project by Amey Realty And Construction LLP in Andheri East, Mumbai 400069, registered with MahaRERA as P51800045221. It was launched in May 2022. It has 69 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Its registered possession date is October 2026, extended by 10 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
49 units booked out of total 69 units (71%).