Borivali New Roma Sadan CHSL, Borivali West
by Sumukh Infraproject · Borivali West, Mumbai 400092 · Map
- Launched
- May 20221 yr 1 mth originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 3 yrs 9 mths
- Concrete structure
- 75%Mid-construction
- Booked (free sale)
- 6 of 786% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 7 units
Rehab16 units for existing members
Total 23 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 20
- 3 BHK
- 3
- Total units
- 23
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 7
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 0% | 6 | |
| 100% | 68% | 0% | 6 | |
| 100% | 50% | 0% | 7 | |
| 0% | 0% | 0% | 6 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 1 mth | 3 yrs |
| Possession date extended | By 3 yrs 9 mths | 3 of 6 |
| Possession date (MahaRERA) | Mar 2027 | Mar 2026 |
| Concrete structure (RCC) | 75% | 88% |
| Units booked (free sale) | 86% | 86% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Kedar Darshan, Borivali West
- Kaveri Heritage, Borivali West
- Zen Enclave, Borivali West
- Om Vasudev Chs Ltd, Borivali West
- Anamika Niwas Chslltd, Borivali West
- Prathamesh Solitaire, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kedar Darshan | May 2022 | April 2027 | 0% | – |
| Kaveri Heritage | May 2022 | March 2026 | 100% | 23 units booked out of total 28 units |
| Zen Enclave | May 2022 | December 2023 | 0% | – |
| Om Vasudev Chs Ltd | May 2022 | March 2026 | 100% | 38 units booked out of total 42 units |
| Anamika Niwas Chslltd | April 2022 | March 2025 | 100% | 14 units booked out of 21 units for sale |
| Prathamesh Solitaire | March 2022 | October 2027 | 77% | 45 units booked out of total 48 units |
About this project
Borivali New Roma Sadan CHSL by Sumukh Infraproject is a 23-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in May 2022 with possession due in March 2027. 6 units booked out of 7 units for sale. The concrete structure (RCC) is 75% complete.
Read full summary
Borivali New Roma Sadan CHSL is a BMC-sanctioned project by Sumukh Infraproject in Borivali West, Mumbai 400092, registered with MahaRERA as P51800045284. It was launched in May 2022. It has 23 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 23 units, 7 are for sale and 16 are rehab units for existing members.
Its registered possession date is March 2027, extended by 3 years 9 months from the original June 2023. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.
6 units booked out of 7 units for sale (86%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 68% to 75%.