Zen Enclave, Borivali West
Lapsed
by Konark Shakti Group Of Companies · Borivali West, Mumbai 400092 · Map
- Launched
- May 20221 yr 7 mths promised
- Possession (MahaRERA)
- Dec 2023Not extendedWhat does Lapsed mean?
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 6
- 2 BHK
- 8
- Other units
- 2
- Total units
- 16
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400092
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 7 mths | 2 yrs 11 mths |
| Possession date extended | No | 3 of 4 |
| Possession date (MahaRERA) | Dec 2023 | Nov 2026 |
| Concrete structure (RCC) | 0% | 88% |
| Units booked | – | 82% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Kedar Darshan, Borivali West
- Borivali New Roma Sadan CHSL, Borivali West
- Kaveri Heritage, Borivali West
- Megha Edge- Red Rose, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kedar Darshan | May 2022 | April 2027 | 0% | – |
| Borivali New Roma Sadan CHSL | May 2022 | March 2027 | 75% | 6 units booked out of 7 units for sale |
| Kaveri Heritage | May 2022 | March 2026 | 100% | 23 units booked out of total 28 units |
| Megha Edge- Red Rose | September 2022 | June 2026 | 100% | 5 units booked out of 8 units for sale |
About this project
Zen Enclave by Konark Shakti Group Of Companies is a 16-unit project in Borivali West, Mumbai 400092, launched in May 2022; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.
Read full summary
Zen Enclave is a project by Konark Shakti Group Of Companies in Borivali West, Mumbai 400092, registered with MahaRERA as P51800035194. It was launched in May 2022. It has 16 units in 1 building: 14 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.