Abundance, Mulund East

Lapsed

by Goodwill Developers · Mulund East, Mumbai 400081 · Map

Launched
May 20223 yrs 7 mths originally promised
Possession (MahaRERA)
Sep 2026Extended by 9 mthsWhat does Lapsed mean?
Concrete structure
90%Mid-construction
Booked
–
Buildings
10.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
14
3 BHK
8
Total units
22
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services6%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 86%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 6%Excavation 100%Concrete structure (RCC) 90%Final finishes 6%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%6%–
100%86%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400081

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths3 yrs 4 mths
Possession date extendedBy 9 mths2 of 3
Possession date (MahaRERA)Sep 2026Apr 2027
Concrete structure (RCC)90%100%
Units booked–91%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Abundance by Goodwill Developers is a 22-unit project in Mulund East, Mumbai 400081, launched in May 2022; its MahaRERA registration has lapsed. The concrete structure (RCC) is 90% complete.

Read full summary

Abundance is a project by Goodwill Developers in Mulund East, Mumbai 400081, registered with MahaRERA as P51800045501. It was launched in May 2022. It has 22 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2026, after an extension of 9 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes 6% complete.

Since the July 2026 update, the reported concrete structure (RCC) has gone from 86% to 90%.