Skip to main content

Lodha Woods, Kandivali East

by Lodha Developers Limited · Kandivali East, Mumbai 400101 · Map

Launched
Jun 2022First of 3 phases
Possession (MahaRERA)
Nov 2027 – Nov 2028Extended in 2 of 3 phases
Concrete structure
98%Weighted across 3 phases
Booked
281 of 28798%
Buildings
30.3 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
4
1 BHK
4
2 BHK
279
Total units
287
Buildings
3
Land
0.3 acres
Phases
3
MahaRERA complaints
3

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Lodha Woods- Tower 8
Mid-construction
P518000461148895%98%
Lodha Woods - Tower 7
Completed
P5180004611888100%98%
Lodha Woods - Tower 6
Nearing possession
P51800046327111100%98%
Show updates by phase

Lodha Woods- Tower 8 (P51800046114)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%10%86
100%85%5%86
100%52%0%86
100%0%0%81

"–" means MahaRERA shows no figure for that update.

Lodha Woods - Tower 7 (P51800046118)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%86
100%100%100%86
100%100%100%86
100%100%0%80

"–" means MahaRERA shows no figure for that update.

Lodha Woods - Tower 6 (P51800046327)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%65%109
100%100%20%109
100%90%0%99
100%52%0%40

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)98%
Finishes, lifts and services59%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 51%Dec 2025: Concrete structure (RCC) 81%Jul 2026: Concrete structure (RCC) 95%Oct 2026: Concrete structure (RCC) 98%Dec 2024: Final finishes 0%Dec 2025: Final finishes 31%Jul 2026: Final finishes 40%Oct 2026: Final finishes 59%Excavation 100%Concrete structure (RCC) 98%Final finishes 59%

How to read construction stages

About this project

Lodha Woods by Lodha Developers Limited is a 287-unit BMC-sanctioned project in Kandivali East, Mumbai 400101, registered with MahaRERA in 3 phases, with possession dates from November 2027 to November 2028. 281 units booked out of total 287 units. The concrete structure (RCC) is 98% complete.

Read full summary

Lodha Woods is a BMC-sanctioned project by Lodha Developers Limited in Kandivali East, Mumbai 400101, registered with MahaRERA as 3 phases (P51800046114, P51800046118, P51800046327). The first phase was launched in June 2022. Together the phases have 287 units in 3 buildings, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. On MahaRERA, 2 are active and 1 is completed.

The phases' registered possession dates run from November 2027 to November 2028; 2 of 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 98% complete and final finishes 59% complete. 2 of the 3 phases have their structure complete.

281 units booked out of total 287 units (98%).

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)

See all Lodha projects →