Ruparel Panache, Santacruz West
Ready to move
by Ruparel Infra & Realty Pvt Ltd · Santacruz West, Mumbai 400054 · Map
- Launched
- Aug 20223 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 100%Ready to move
- Booked
- 138 of 14893% · 133 in Jul 2026
- Buildings
- 30.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 14
- 2 BHK
- 46
- 3 BHK
- 71
- 4 BHK
- 5
- Other units
- 12
- Total units
- 148
- Buildings
- 3
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 70
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 138 | |
| 100% | 100% | 95% | 133 | |
| 100% | 100% | 90% | 128 | |
| 0% | 0% | 0% | 42 |
"–" means MahaRERA shows no figure for that update.
About this project
Ruparel Panache by Ruparel Infra & Realty Pvt Ltd is a 148-unit SRA-sanctioned project in Santacruz West, Mumbai 400054, launched in August 2022 with possession due in December 2026. 138 units booked out of total 148 units. The concrete structure (RCC) is complete.
Read full summary
Ruparel Panache is an SRA-sanctioned project by Ruparel Infra & Realty Pvt Ltd in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800046597. It was launched in August 2022. It has 148 units in 3 buildings: 136 homes (1, 2, 3 and 4 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
138 units booked out of total 148 units (93%). Since the July 2026 update, 5 more units have been booked.
Ruparel's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.