Ruparel Panache, Santacruz West

Ready to move

by Ruparel Infra & Realty Pvt Ltd · Santacruz West, Mumbai 400054 · Map

Launched
Aug 20223 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Ready to move
Booked
138 of 14893% · 133 in Jul 2026
Buildings
30.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
14
2 BHK
46
3 BHK
71
4 BHK
5
Other units
12
Total units
148
Buildings
3
Land
0.8 acres
Phases
1
MahaRERA complaints
0
Reserved units
70

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 90%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%138
100%100%95%133
100%100%90%128
0%0%0%42

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ruparel Panache by Ruparel Infra & Realty Pvt Ltd is a 148-unit SRA-sanctioned project in Santacruz West, Mumbai 400054, launched in August 2022 with possession due in December 2026. 138 units booked out of total 148 units. The concrete structure (RCC) is complete.

Read full summary

Ruparel Panache is an SRA-sanctioned project by Ruparel Infra & Realty Pvt Ltd in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800046597. It was launched in August 2022. It has 148 units in 3 buildings: 136 homes (1, 2, 3 and 4 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

138 units booked out of total 148 units (93%). Since the July 2026 update, 5 more units have been booked.

Ruparel's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA28
Total units across these projects6,570
Completed without extending the possession date0
Completed after an extension1
Lapsed12
Under construction15
Possession date extended on the builder's application14
Typical time from launch to 100% structure5 years 9 months
MahaRERA complaints (filed by or against the builder), all Ruparel projects872 (22 of 28 projects)

See all Ruparel projects →