Silver Rock By S Raheja, Khar West

Lapsed

by S. Raheja Infrastructure Private Limited · Khar West, Mumbai 400052 · Map

Launched
Aug 20223 yrs 10 mths promised
Possession (MahaRERA)
Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
2 of 2100%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
2
Total units
2
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%2
100%100%0%2
100%100%0%2
100%100%0%10

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Silver Rock By S Raheja by S. Raheja Infrastructure Private Limited is a 2-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in August 2022; its MahaRERA registration has lapsed. 2 units booked out of total 2 units. The concrete structure (RCC) is complete.

Read full summary

Silver Rock By S Raheja is a BMC-sanctioned project by S. Raheja Infrastructure Private Limited in Khar West, Mumbai 400052, registered with MahaRERA as P51800046602. It was launched in August 2022. It has 2 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.

2 units booked out of total 2 units (100%).