JP Parkway, Jogeshwari East
by Srushti Raj Developers LLP · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Sep 20226 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 55%Mid-construction
- Booked
- 354 of 49971% · 287 in Jul 2026
- Buildings
- 30.5 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 335
- 2 BHK
- 145
- Other units
- 19
- Total units
- 499
- Buildings
- 3
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 55% | 0% | 354 | |
| 100% | 42% | 0% | 287 | |
| 100% | 0% | 0% | 220 | |
| 100% | 0% | 0% | 102 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400060
Projects with 200–1,000 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 3 mths | 4 yrs 4 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2028 | Mar 2027 |
| Concrete structure (RCC) | 55% | 100% |
| Units booked | 71% | 64% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 3 projects
- Uk Iona, Jogeshwari East
- AIM Garden, Jogeshwari East
- Edenrose, Jogeshwari East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Uk Iona | November 2022 | Dec 2026 – Dec 2027 | 100% | 156 units booked out of total 244 units |
| AIM Garden | December 2022 | July 2029 | 100% | 111 units booked out of 163 units for sale |
| Edenrose | February 2023 | March 2027 | 0% | 0 units booked out of total 293 units |
About this project
JP Parkway by Srushti Raj Developers LLP is a 499-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in September 2022 with possession due in December 2028. 354 units booked out of total 499 units. The concrete structure (RCC) is 55% complete.
Read full summary
JP Parkway is an SRA-sanctioned project by Srushti Raj Developers LLP in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800046839. It was launched in September 2022. It has 499 units in 3 buildings: 480 homes (1 and 2 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 55% complete, final finishes not started.
354 units booked out of total 499 units (71%). Since the July 2026 update, 67 more units have been booked and the reported concrete structure (RCC) has gone from 42% to 55%.