AIM Garden, Jogeshwari East

Ready to move

by AIM Developers · Jogeshwari East, Mumbai 400060 · Map

Launched
Dec 20226 yrs 7 mths promised
Possession (MahaRERA)
Jul 2029Not extended
Concrete structure
100%Ready to move
Booked (free sale)
111 of 16368% · 128 rehab units
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale111 booked out of 163 units

Rehab128 units for existing members

Total 291 units. Rehab units are not for sale.

Project facts

1 RK
106
1 BHK
93
2 BHK
39
Other units
53
Total units
291
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
163
Rehab units
128

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 90%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%111
100%100%90%108
100%75%0%99
100%50%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400060

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400060
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 7 mths4 yrs 2 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)Jul 2029Jul 2027
Concrete structure (RCC)100%96%
Units booked (free sale)68%67%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

AIM Garden by AIM Developers is a 291-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in December 2022 with possession due in July 2029. 111 units booked out of 163 units for sale. The concrete structure (RCC) is complete.

Read full summary

AIM Garden is an SRA-sanctioned project by AIM Developers in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800047985. It was launched in December 2022. It has 291 units in 1 building: 238 homes (1 RK, 1 BHK and 2 BHK) and 53 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 291 units, 163 are for sale and 128 are rehab units for existing members.

Its registered possession date is July 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

111 units booked out of 163 units for sale (68%). Since the July 2026 update, 3 more units have been booked.