Skip to main content

Om Ambe Smruti, Mulund West

Ready to move

by Oscar Infrastructure Private Limited · Mulund West, Mumbai 400080 · Map

Launched
Sep 20222 yrs 3 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 2 yrs 4 mths
Concrete structure
100%Ready to move
Booked (free sale)
27 of 27100% · 44 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale27 booked out of 27 units

Rehab44 units for existing members

Total 71 units. Rehab units are not for sale.

Project facts

1 BHK
9
2 BHK
39
3 BHK
14
Other units
9
Total units
71
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
27
Rehab units
44

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 30%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%27
100%100%95%27
100%100%30%25
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths3 yrs 6 mths
Possession date extendedBy 2 yrs 4 mths4 of 6
Possession date (MahaRERA)Apr 2027Jan 2027
Concrete structure (RCC)100%85%
Units booked (free sale)100%35%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Om Ambe Smruti by Oscar Infrastructure Private Limited is a 71-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in September 2022 with possession due in April 2027. 27 units booked out of 27 units for sale. The concrete structure (RCC) is complete.

Read full summary

Om Ambe Smruti is a BMC-sanctioned project by Oscar Infrastructure Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800046923. It was launched in September 2022. It has 71 units in 1 building: 62 homes (1, 2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 71 units, 27 are for sale and 44 are rehab units for existing members.

Its registered possession date is April 2027, extended by 2 years 4 months from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

27 units booked out of 27 units for sale (100%).