Shree Siidha Pride, Mulund West
by Ganalaxmi Homes · Mulund West, Mumbai 400080 · Map
- Launched
- Nov 20225 yrs 1 mth promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 22 of 2879%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale22 booked out of 28 units
Land-owner share12 units, not for sale
Total 40 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 20
- 2 BHK
- 17
- Other units
- 3
- Total units
- 40
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 28
- Land-owner share (not for sale)
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 22 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 1 mth | 2 yrs 6 mths |
| Possession date extended | No | 4 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Nov 2026 |
| Concrete structure (RCC) | 0% | 98% |
| Units booked (free sale) | 79% | 80% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Kusum Classic of Pulivahana CHS Ltd, Mulund West
- The New Anand Deep Chs Ltd, Mulund West
- Austin Heights, Mulund West
- Tirupati Apartments Chsl, Mulund West
- Shivram CHSL - Phase 3, Mulund West
- Om Ambe Smruti, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kusum Classic of Pulivahana CHS Ltd | November 2022 | December 2026 | 85% | 2 units booked out of 17 units for sale |
| The New Anand Deep Chs Ltd | December 2022 | September 2026 | 95% | 28 units booked out of 28 units for sale |
| Austin Heights | December 2022 | October 2029 | 0% | – |
| Tirupati Apartments Chsl | January 2023 | October 2026 | 100% | 16 units booked out of 20 units for sale |
| Shivram CHSL - Phase 3 | January 2023 | December 2025 | 100% | 19 units booked out of total 48 units |
| Om Ambe Smruti | September 2022 | April 2027 | 100% | 27 units booked out of 27 units for sale |
About this project
Shree Siidha Pride by Ganalaxmi Homes is a 40-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in November 2022 with possession due in December 2027. 22 units booked out of 28 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Shree Siidha Pride is a BMC-sanctioned project by Ganalaxmi Homes in Mulund West, Mumbai 400080, registered with MahaRERA as P51800047845. It was launched in November 2022. It has 40 units in 1 building: 37 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 40 units, 28 are for sale and 12 are the land-owner's share, not for sale.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
22 units booked out of 28 units for sale (79%).