Mangal Meeth Chs Ltd, Juhu
Ready to move
by Aspen Real Estate Developers LLP · Juhu, Mumbai 400049 · Map
- Launched
- Sep 20223 yrs 3 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 1 yr 4 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 5 of 862% · 10 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 8 units
Rehab10 units for existing members
Total 18 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 4
- 3 BHK
- 4
- 4 BHK
- 9
- 5+ BHK
- 1
- Total units
- 18
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 8
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 5 | |
| 100% | 100% | 100% | 4 | |
| 100% | 100% | 60% | 3 | |
| 100% | 100% | 34% | 3 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400049
Projects with up to 40 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 3 yrs 7 mths |
| Possession date extended | By 1 yr 4 mths | 2 of 4 |
| Possession date (MahaRERA) | Apr 2027 | Jun 2028 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 62% | 67% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- New Brindavan CHSL, Juhu
- Aditya Chsl, Juhu
- K L Valeria, Juhu
- 46 Juhu, Juhu
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| New Brindavan CHSL | August 2022 | December 2029 | 100% | 8 units booked out of 10 units for sale |
| Aditya Chsl | August 2022 | December 2026 | 100% | – |
| K L Valeria | April 2023 | September 2026 | 100% | 4 units booked out of 6 units for sale |
| 46 Juhu | August 2023 | April 2030 | 0% | 0 units booked out of total 8 units |
About this project
Mangal Meeth Chs Ltd by Aspen Real Estate Developers LLP is an 18-unit MHADA-sanctioned project in Juhu, Mumbai 400049, launched in September 2022 with possession due in April 2027. 5 units booked out of 8 units for sale. The concrete structure (RCC) is complete.
Read full summary
Mangal Meeth Chs Ltd is a MHADA-sanctioned project by Aspen Real Estate Developers LLP in Juhu, Mumbai 400049, registered with MahaRERA as P51800047039. It was launched in September 2022. It has 18 units in 1 building, with 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 8 are for sale and 10 are rehab units for existing members.
Its registered possession date is April 2027, extended by 1 year 4 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
5 units booked out of 8 units for sale (62%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from December 2025 to April 2027.