- Launched
- Apr 20232 yrs 5 mths originally promised
- Possession (MahaRERA)
- Sep 2026Extended by 1 yr
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 4 of 667% · 10 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 6 units
Rehab10 units for existing members
Total 16 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 4
- 2 BHK
- 4
- 3 BHK
- 5
- 4 BHK
- 2
- Other units
- 1
- Total units
- 16
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 6
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 4 | |
| 100% | 100% | 50% | 4 | |
| 100% | 50% | 30% | 4 | |
| 75% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400049
Projects with up to 30 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 3 yrs 3 mths |
| Possession date extended | By 1 yr | 2 of 3 |
| Possession date (MahaRERA) | Sep 2026 | Apr 2027 |
| Concrete structure (RCC) | 100% | 100% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- 46 Juhu, Juhu
- Mangal Meeth Chs Ltd, Juhu
- Aditya Chsl, Juhu
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| 46 Juhu | August 2023 | April 2030 | 0% | 0 units booked out of total 8 units |
| Mangal Meeth Chs Ltd | September 2022 | April 2027 | 100% | 5 units booked out of 8 units for sale |
| Aditya Chsl | August 2022 | December 2026 | 100% | – |
About this project
K L Valeria by K L Housing LLP is a 16-unit BMC-sanctioned project in Juhu, Mumbai 400049, launched in April 2023 with possession due in September 2026. 4 units booked out of 6 units for sale. The concrete structure (RCC) is complete.
Read full summary
K L Valeria is a BMC-sanctioned project by K L Housing LLP in Juhu, Mumbai 400049, registered with MahaRERA as P51800050591. It was launched in April 2023. It has 16 units in 1 building: 15 homes (1, 2, 3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 16 units, 6 are for sale and 10 are rehab units for existing members.
Possession was due in September 2026, after an extension of 1 year from the original September 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
4 units booked out of 6 units for sale (67%).