33 West, Khar West
by Silver Lifespaces Private Limited · Khar West, Mumbai 400052 · Map
- Launched
- Oct 20222 yrs 2 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 2 yrs
- Concrete structure
- 95%Mid-construction
- Booked
- 4 of 1040%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 9
- Other units
- 1
- Total units
- 10
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 0% | 4 | |
| 100% | 85% | 0% | 4 | |
| 100% | 85% | 0% | 4 | |
| 100% | 76% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400052
Projects with up to 20 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 2 mths | 2 yrs 1 mth |
| Possession date extended | By 2 yrs | 2 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 95% | 80% |
| Units booked | 40% | 22% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Bhagirathi Sadan, Khar West
- Khar Hari Niketan, Khar West
- Yogi Sea, Khar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bhagirathi Sadan | December 2022 | January 2025 | 80% | 2 units booked out of total 9 units |
| Khar Hari Niketan | December 2022 | December 2026 | 0% | 4 units booked out of total 13 units |
| Yogi Sea | April 2023 | January 2027 | 100% | 1 unit booked out of total 7 units |
About this project
33 West by Silver Lifespaces Private Limited is a 10-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in October 2022 with possession due in December 2026. 4 units booked out of total 10 units. The concrete structure (RCC) is 95% complete.
Read full summary
33 West is a BMC-sanctioned project by Silver Lifespaces Private Limited in Khar West, Mumbai 400052, registered with MahaRERA as P51800047213. It was launched in October 2022. It has 10 units in 1 building: 9 homes (4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.
4 units booked out of total 10 units (40%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 85% to 95% and the possession date has moved from December 2025 to December 2026.