- Launched
- Dec 20222 yrs 1 mth promised
- Possession (MahaRERA)
- Jan 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 80%Mid-construction
- Booked
- 2 of 922%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 8
- 4 BHK
- 1
- Total units
- 9
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 30% | 2 | |
| 100% | 80% | 30% | – | |
| 100% | 80% | 30% | – | |
| 100% | 80% | 30% | 2 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400052
Projects with up to 20 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 1 mth | 2 yrs 2 mths |
| Possession date extended | No | 3 of 3 |
| Possession date (MahaRERA) | Jan 2025 | Dec 2026 |
| Concrete structure (RCC) | 80% | 95% |
| Units booked | 22% | 31% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Khar Hari Niketan, Khar West
- 33 West, Khar West
- Yogi Sea, Khar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Khar Hari Niketan | December 2022 | December 2026 | 0% | 4 units booked out of total 13 units |
| 33 West | October 2022 | December 2026 | 95% | 4 units booked out of total 10 units |
| Yogi Sea | April 2023 | January 2027 | 100% | 1 unit booked out of total 7 units |
About this project
Bhagirathi Sadan by L Nagpal Developers is a 9-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in December 2022; its MahaRERA registration has lapsed. 2 units booked out of total 9 units. The concrete structure (RCC) is 80% complete.
Read full summary
Bhagirathi Sadan is a BMC-sanctioned project by L Nagpal Developers in Khar West, Mumbai 400052, registered with MahaRERA as P51800048002. It was launched in December 2022. It has 9 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in January 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes 30% complete.
2 units booked out of total 9 units (22%).