Bhagirathi Sadan, Khar West

Lapsed

by L Nagpal Developers · Khar West, Mumbai 400052 · Map

Launched
Dec 20222 yrs 1 mth promised
Possession (MahaRERA)
Jan 2025Not extendedWhat does Lapsed mean?
Concrete structure
80%Mid-construction
Booked
2 of 922%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
8
4 BHK
1
Total units
9
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 30%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 80%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%30%2
100%80%30%–
100%80%30%–
100%80%30%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400052

Projects with up to 20 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400052
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 1 mth2 yrs 2 mths
Possession date extendedNo3 of 3
Possession date (MahaRERA)Jan 2025Dec 2026
Concrete structure (RCC)80%95%
Units booked22%31%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Bhagirathi Sadan by L Nagpal Developers is a 9-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in December 2022; its MahaRERA registration has lapsed. 2 units booked out of total 9 units. The concrete structure (RCC) is 80% complete.

Read full summary

Bhagirathi Sadan is a BMC-sanctioned project by L Nagpal Developers in Khar West, Mumbai 400052, registered with MahaRERA as P51800048002. It was launched in December 2022. It has 9 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in January 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes 30% complete.

2 units booked out of total 9 units (22%).