Rajlaxmi Heights Chsl, Borivali East

by Rajmudra Constructions Private Limited · Borivali East, Mumbai 400066 · Map

Launched
Oct 20222 yrs 7 mths originally promised
Possession (MahaRERA)
Sep 2027Extended by 2 yrs 4 mths
Concrete structure
91%Mid-construction
Booked (free sale)
15 of 3148% · 17 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale15 booked out of 31 units

Rehab17 units for existing members

Total 48 units. Rehab units are not for sale.

Project facts

1 RK
10
1 BHK
20
2 BHK
18
Total units
48
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
31
Rehab units
17

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)91%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 63%Jul 2026: Concrete structure (RCC) 91%Oct 2026: Concrete structure (RCC) 91%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 91%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%91%0%15
100%91%0%15
100%63%0%11
100%50%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400066

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 7 mths3 yrs 10 mths
Possession date extendedBy 2 yrs 4 mths2 of 4
Possession date (MahaRERA)Sep 2027Dec 2026
Concrete structure (RCC)91%98%
Units booked (free sale)48%34%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Rajlaxmi Heights Chsl by Rajmudra Constructions Private Limited is a 48-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in October 2022 with possession due in September 2027. 15 units booked out of 31 units for sale. The concrete structure (RCC) is 91% complete.

Read full summary

Rajlaxmi Heights Chsl is a BMC-sanctioned project by Rajmudra Constructions Private Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800047301. It was launched in October 2022. It has 48 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 48 units, 31 are for sale and 17 are rehab units for existing members.

Its registered possession date is September 2027, extended by 2 years 4 months from the original May 2025. Construction: excavation complete, structure (RCC) 91% complete, final finishes not started.

15 units booked out of 31 units for sale (48%). Since the July 2026 update, the possession date has moved from May 2026 to September 2027.