Rajlaxmi Heights Chsl, Borivali East
by Rajmudra Constructions Private Limited · Borivali East, Mumbai 400066 · Map
- Launched
- Oct 20222 yrs 7 mths originally promised
- Possession (MahaRERA)
- Sep 2027Extended by 2 yrs 4 mths
- Concrete structure
- 91%Mid-construction
- Booked (free sale)
- 15 of 3148% · 17 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale15 booked out of 31 units
Rehab17 units for existing members
Total 48 units. Rehab units are not for sale.
Project facts
- 1 RK
- 10
- 1 BHK
- 20
- 2 BHK
- 18
- Total units
- 48
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 31
- Rehab units
- 17
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 91% | 0% | 15 | |
| 100% | 91% | 0% | 15 | |
| 100% | 63% | 0% | 11 | |
| 100% | 50% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400066
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 7 mths | 3 yrs 10 mths |
| Possession date extended | By 2 yrs 4 mths | 2 of 4 |
| Possession date (MahaRERA) | Sep 2027 | Dec 2026 |
| Concrete structure (RCC) | 91% | 98% |
| Units booked (free sale) | 48% | 34% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Ashtha Buoyancy - IBTC Borivali East, Borivali East
- Shree Krupa Chsl, Borivali East
- Rajendra Nagar Raj Kiran Co.Op. Hsg. Soc. Ltd, Borivali East
- Zenon, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ashtha Buoyancy - IBTC Borivali East | December 2022 | December 2026 | 97% | 16 units booked out of 88 units for sale |
| Shree Krupa Chsl | January 2023 | December 2026 | 100% | 48 units booked out of total 51 units |
| Rajendra Nagar Raj Kiran Co.Op. Hsg. Soc. Ltd | April 2022 | December 2026 | 100% | 4 units booked out of 62 units for sale |
| Zenon | April 2022 | December 2026 | 76% | 58 units booked out of total 115 units |
About this project
Rajlaxmi Heights Chsl by Rajmudra Constructions Private Limited is a 48-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in October 2022 with possession due in September 2027. 15 units booked out of 31 units for sale. The concrete structure (RCC) is 91% complete.
Read full summary
Rajlaxmi Heights Chsl is a BMC-sanctioned project by Rajmudra Constructions Private Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800047301. It was launched in October 2022. It has 48 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 48 units, 31 are for sale and 17 are rehab units for existing members.
Its registered possession date is September 2027, extended by 2 years 4 months from the original May 2025. Construction: excavation complete, structure (RCC) 91% complete, final finishes not started.
15 units booked out of 31 units for sale (48%). Since the July 2026 update, the possession date has moved from May 2026 to September 2027.