Ashtha Buoyancy - IBTC Borivali East, Borivali East
by Indo Build Enterprise · Borivali East, Mumbai 400066 · Map
- Launched
- Dec 20224 yrs promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 97%Mid-construction
- Booked (free sale)
- 16 of 8818% · 31 rehab units
- Buildings
- 30.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale16 booked out of 88 units
Rehab31 units for existing members
Total 119 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 43
- 2 BHK
- 43
- Other units
- 31
- Total units
- 119
- Buildings
- 3
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 88
- Rehab units
- 31
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 0% | 16 | |
| 100% | 97% | 0% | 16 | |
| 100% | 33% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400066
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs | 3 yrs 1 mth |
| Possession date extended | No | 2 of 4 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 97% | 94% |
| Units booked (free sale) | 18% | 55% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Shree Krupa Chsl, Borivali East
- Rajlaxmi Heights Chsl, Borivali East
- Vastu Shilp, Borivali East
- 71P, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shree Krupa Chsl | January 2023 | December 2026 | 100% | 48 units booked out of total 51 units |
| Rajlaxmi Heights Chsl | October 2022 | September 2027 | 91% | 15 units booked out of 31 units for sale |
| Vastu Shilp | May 2023 | December 2026 | 96% | 20 units booked out of 88 units for sale |
| 71P | June 2023 | December 2026 | 41% | 21 units booked out of 34 units for sale |
About this project
Ashtha Buoyancy - IBTC Borivali East by Indo Build Enterprise is a 119-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in December 2022 with possession due in December 2026. 16 units booked out of 88 units for sale. The concrete structure (RCC) is 97% complete.
Read full summary
Ashtha Buoyancy - IBTC Borivali East is an SRA-sanctioned project by Indo Build Enterprise in Borivali East, Mumbai 400066, registered with MahaRERA as P51800048360. It was launched in December 2022. It has 119 units in 3 buildings: 88 homes (1 RK, 1 BHK and 2 BHK) and 31 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 119 units, 88 are for sale and 31 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 97% complete, final finishes not started.
16 units booked out of 88 units for sale (18%).