Chembur Deep Jyoti Chs Ltd, Chembur
by P M Developers · Chembur, Mumbai 400071 · Map
- Launched
- Oct 20223 yrs 9 mths originally promised
- Possession (MahaRERA)
- Nov 2027Extended by 1 yr 4 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 88 of 10485%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale88 booked out of 104 units
Land-owner share20 units, not for sale
Total 124 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 85
- 3 BHK
- 30
- Other units
- 8
- Total units
- 124
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 104
- Land-owner share (not for sale)
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 88 | |
| 100% | 88% | 65% | 86 | |
| 100% | 50% | 0% | – | |
| 100% | 25% | 0% | 26 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400071
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 3 yrs |
| Possession date extended | By 1 yr 4 mths | 3 of 4 |
| Possession date (MahaRERA) | Nov 2027 | Nov 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 85% | 88% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Queens Park, Chembur
- Tigon Elite, Chembur
- Arham Arya, Chembur
- Janki Heritage, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Queens Park | October 2022 | October 2026 | 100% | 99 units booked out of 124 units for sale |
| Tigon Elite | October 2022 | December 2026 | 100% | 75 units booked out of 76 units for sale |
| Arham Arya | February 2023 | December 2026 | 100% | 46 units booked out of 48 units for sale |
| Janki Heritage | June 2022 | December 2025 | 100% | 17 units booked out of 42 units for sale |
About this project
Chembur Deep Jyoti Chs Ltd by P M Developers is a 124-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in October 2022 with possession due in November 2027. 88 units booked out of 104 units for sale. The concrete structure (RCC) is complete.
Read full summary
Chembur Deep Jyoti Chs Ltd is a MHADA-sanctioned project by P M Developers in Chembur, Mumbai 400071, registered with MahaRERA as P51800047359. It was launched in October 2022. It has 124 units in 1 building: 116 homes (1, 2 and 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 124 units, 104 are for sale and 20 are the land-owner's share, not for sale.
Its registered possession date is November 2027, extended by 1 year 4 months from the original July 2026. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
88 units booked out of 104 units for sale (85%). Since the July 2026 update, 2 more units have been booked, the reported concrete structure (RCC) has gone from 88% to 100% and the possession date has moved from July 2026 to November 2027.