Queens Park, Chembur

Ready to moveLapsed

by V Laxmi Estate Developers Private Limited · Chembur, Mumbai 400071 · Map

Launched
Oct 20223 yrs 2 mths originally promised
Possession (MahaRERA)
Oct 2026Extended by 10 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
99 of 12480% · 36 rehab units
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale99 booked out of 124 units

Rehab36 units for existing members

Total 160 units. Rehab units are not for sale.

Project facts

1 BHK
29
2 BHK
91
3 BHK
15
Other units
25
Total units
160
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
124
Rehab units
36

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 45%Dec 2025: Excavation 45%Jul 2026: Excavation 45%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%99
45%0%0%–
45%0%0%–
45%0%0%75

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400071

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 2 mths3 yrs 9 mths
Possession date extendedBy 10 mths2 of 3
Possession date (MahaRERA)Oct 2026Dec 2026
Concrete structure (RCC)100%100%
Units booked (free sale)80%96%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Queens Park by V Laxmi Estate Developers Private Limited is a 160-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in October 2022; its MahaRERA registration has lapsed. 99 units booked out of 124 units for sale. The concrete structure (RCC) is complete.

Read full summary

Queens Park is a MHADA-sanctioned project by V Laxmi Estate Developers Private Limited in Chembur, Mumbai 400071, registered with MahaRERA as P51800047377. It was launched in October 2022. It has 160 units in 2 buildings: 135 homes (1, 2 and 3 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 160 units, 124 are for sale and 36 are rehab units for existing members.

Its registered possession date is October 2026, extended by 10 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

99 units booked out of 124 units for sale (80%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from December 2025 to October 2026.