Gami and Jaydeep Elanza, Chembur
Ready to moveLapsed
by M/S Real Infrastructure Co · Chembur, Mumbai 400089 · Map
- Launched
- Oct 20223 yrs 2 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 114 of 13982% · 36 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale114 booked out of 139 units
Rehab36 units for existing members
Total 175 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 16
- 2 BHK
- 119
- 3 BHK
- 32
- Other units
- 8
- Total units
- 175
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 139
- Rehab units
- 36
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 114 | |
| 100% | 100% | 100% | 114 | |
| 100% | 100% | 50% | 105 | |
| 100% | 94% | 0% | 20 |
"–" means MahaRERA shows no figure for that update.
About this project
Gami and Jaydeep Elanza by M/S Real Infrastructure Co is a 175-unit MHADA-sanctioned project in Chembur, Mumbai 400089, launched in October 2022; its MahaRERA registration has lapsed. 114 units booked out of 139 units for sale. The concrete structure (RCC) is complete.
Read full summary
Gami and Jaydeep Elanza is a MHADA-sanctioned project by M/S Real Infrastructure Co in Chembur, Mumbai 400089, registered with MahaRERA as P51800047428. It was launched in October 2022. It has 175 units in 2 buildings: 167 homes (1, 2 and 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 175 units, 139 are for sale and 36 are rehab units for existing members.
Possession was due in June 2026, after an extension of 6 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
114 units booked out of 139 units for sale (82%).