Lodha Vikhroli-Signet, Vikhroli

by Lodha Developers Limited · Vikhroli, Mumbai 400079 · Map

Launched
Nov 20224 yrs 7 mths originally promised
Possession (MahaRERA)
Jun 2029Extended by 2 yrs
Concrete structure
77%Mid-construction
Booked
642 of 90771% · 634 in Jul 2026
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
907
Total units
907
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)77%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 38%Oct 2026: Concrete structure (RCC) 77%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 77%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%77%0%642
100%38%0%634
100%0%0%560
100%10%0%427

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Lodha Vikhroli-Signet by Lodha Developers Limited is a 907-unit SRA-sanctioned project in Vikhroli, Mumbai 400079, launched in November 2022 with possession due in June 2029. 642 units booked out of total 907 units. The concrete structure (RCC) is 77% complete.

Read full summary

Lodha Vikhroli-Signet is an SRA-sanctioned project by Lodha Developers Limited in Vikhroli, Mumbai 400079, registered with MahaRERA as P51800047504. It was launched in November 2022. It has 907 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2029, extended by 2 years from the original June 2027. Construction: excavation complete, structure (RCC) 77% complete, final finishes not started.

642 units booked out of total 907 units (71%). Since the July 2026 update, 8 more units have been booked, the reported concrete structure (RCC) has gone from 38% to 77% and the possession date has moved from June 2028 to June 2029.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)

See all Lodha projects →