Hareshwar Pride, Kurla East

by Satyadeep Realtors Pvt Ltd · Kurla East, Mumbai 400024 · Map

Launched
Nov 20223 yrs 1 mth originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
5%Mid-construction
Booked (free sale)
70 of 9375% · 41 rehab units
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale70 booked out of 93 units

Rehab41 units for existing members

Total 134 units. Rehab units are not for sale.

Project facts

1 BHK
46
2 BHK
88
Total units
134
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
93
Rehab units
41
Reserved units
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)5%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 5%Oct 2026: Concrete structure (RCC) 5%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 5%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%5%0%70
100%5%0%70
100%5%0%36
100%5%0%10

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400024

Projects with 60–300 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400024
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth3 yrs 8 mths
Possession date extendedBy 1 yr1 of 3
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)5%100%
Units booked (free sale)75%98%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Hareshwar Pride by Satyadeep Realtors Pvt Ltd is a 134-unit MHADA-sanctioned project in Kurla East, Mumbai 400024, launched in November 2022 with possession due in December 2026. 70 units booked out of 93 units for sale. The concrete structure (RCC) is 5% complete.

Read full summary

Hareshwar Pride is a MHADA-sanctioned project by Satyadeep Realtors Pvt Ltd in Kurla East, Mumbai 400024, registered with MahaRERA as P51800047786. It was launched in November 2022. It has 134 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 134 units, 93 are for sale and 41 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 5% complete, final finishes not started.

70 units booked out of 93 units for sale (75%).