Ekdanta, Kurla East

Ready to moveLapsed

by Ekdanta Constructions and Developers · Kurla East, Mumbai 400024 · Map

Launched
Apr 20223 yrs 8 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
106 of 10799% · 40 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale106 booked out of 107 units

Rehab40 units for existing members

Total 147 units. Rehab units are not for sale.

Project facts

1 BHK
80
2 BHK
67
Total units
147
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
107
Rehab units
40

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 15%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%106
100%90%50%–
100%90%50%–
100%100%15%90

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400024

Projects with 70–300 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400024
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 11 mths
Possession date extendedNo3 of 4
Possession date (MahaRERA)Dec 2025Dec 2026
Concrete structure (RCC)100%54%
Units booked (free sale)99%75%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Ekdanta by Ekdanta Constructions and Developers is a 147-unit MHADA-sanctioned project in Kurla East, Mumbai 400024, launched in April 2022; its MahaRERA registration has lapsed. 106 units booked out of 107 units for sale. The concrete structure (RCC) is complete.

Read full summary

Ekdanta is a MHADA-sanctioned project by Ekdanta Constructions and Developers in Kurla East, Mumbai 400024, registered with MahaRERA as P51800034572. It was launched in April 2022. It has 147 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 147 units, 107 are for sale and 40 are rehab units for existing members.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

106 units booked out of 107 units for sale (99%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 90% to 100%.