Shree Vallabh, Kandivali West
by Mamtora Enterprise · Kandivali West, Mumbai 400067 · Map
- Launched
- Dec 20222 yrs 9 mths originally promised
- Possession (MahaRERA)
- Sep 2026Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 11 of 4127% · 17 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale11 booked out of 41 units
Rehab17 units for existing members
Land-owner share5 units, not for sale
Total 63 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 12
- 2 BHK
- 24
- 3 BHK
- 12
- Other units
- 15
- Total units
- 63
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 41
- Rehab units
- 17
- Land-owner share (not for sale)
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 56% | 11 | |
| 100% | 100% | 7% | 6 | |
| 95% | 93% | 0% | 6 | |
| 80% | 27% | 0% | 5 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 3 yrs 8 mths |
| Possession date extended | By 1 yr | 1 of 6 |
| Possession date (MahaRERA) | Sep 2026 | Nov 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 27% | 54% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Muncipal Employees Deep Darshan Co Operative Housing Society Limited, Kandivali West
- Charkop Ramvijay Chs Ltd, Kandivali West
- Self Redevelopment Of Charkop Shalimar Chs Ltd, Kandivali West
- Kandivali Hanuman Co-op Housing Society Ltd, Kandivali West
- Sunder Baug Chsl, Kandivali West
- Laxmi Heights, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Muncipal Employees Deep Darshan Co Operative Housing Society Limited | December 2022 | December 2025 | 100% | 15 units booked out of 25 units for sale |
| Charkop Ramvijay Chs Ltd | February 2023 | December 2026 | 100% | 22 units booked out of 33 units for sale |
| Self Redevelopment Of Charkop Shalimar Chs Ltd | October 2022 | December 2026 | 100% | 37 units booked out of 38 units for sale |
| Kandivali Hanuman Co-op Housing Society Ltd | March 2023 | November 2026 | 100% | 28 units booked out of total 59 units |
| Sunder Baug Chsl | April 2023 | December 2026 | 70% | 24 units booked out of total 54 units |
| Laxmi Heights | April 2023 | September 2026 | 60% | 1 unit booked out of total 23 units |
About this project
Shree Vallabh by Mamtora Enterprise is a 63-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in December 2022 with possession due in September 2026. 11 units booked out of 41 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shree Vallabh is a BMC-sanctioned project by Mamtora Enterprise in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800047875. It was launched in December 2022. It has 63 units in 1 building: 48 homes (1, 2 and 3 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 63 units, 41 are for sale, 17 are rehab units for existing members and 5 are the land-owner's share, not for sale.
Possession was due in September 2026, after an extension of 1 year from the original September 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 56% complete.
11 units booked out of 41 units for sale (27%). Since the July 2026 update, 5 more units have been booked.