Self Redevelopment Of Charkop Shalimar Chs Ltd, Kandivali West
Ready to move
by Charkop Shalimar Chs Ltd · Kandivali West, Mumbai 400067 · Map
- Launched
- Oct 20224 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 37 of 3897% · 23 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale37 booked out of 38 units
Rehab23 units for existing members
Total 61 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 16
- 2 BHK
- 32
- 3 BHK
- 8
- Other units
- 5
- Total units
- 61
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 38
- Rehab units
- 23
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 37 | |
| 100% | 100% | 85% | 37 | |
| 100% | 100% | 50% | 35 | |
| 100% | 95% | 0% | 33 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400067
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 2 mths | 3 yrs 4 mths |
| Possession date extended | No | 2 of 4 |
| Possession date (MahaRERA) | Dec 2026 | Nov 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 97% | 54% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Shree Vallabh, Kandivali West
- Muncipal Employees Deep Darshan Co Operative Housing Society Limited, Kandivali West
- Charkop Ramvijay Chs Ltd, Kandivali West
- Jade Chsl, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shree Vallabh | December 2022 | September 2026 | 100% | 11 units booked out of 41 units for sale |
| Muncipal Employees Deep Darshan Co Operative Housing Society Limited | December 2022 | December 2025 | 100% | 15 units booked out of 25 units for sale |
| Charkop Ramvijay Chs Ltd | February 2023 | December 2026 | 100% | 22 units booked out of 33 units for sale |
| Jade Chsl | June 2022 | December 2029 | 85% | 10 units booked out of 21 units for sale |
About this project
Self Redevelopment Of Charkop Shalimar Chs Ltd by Charkop Shalimar Chs Ltd is a 61-unit MHADA-sanctioned project in Kandivali West, Mumbai 400067, launched in October 2022 with possession due in December 2026. 37 units booked out of 38 units for sale. The concrete structure (RCC) is complete.
Read full summary
Self Redevelopment Of Charkop Shalimar Chs Ltd is a MHADA-sanctioned project by Charkop Shalimar Chs Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800047429. It was launched in October 2022. It has 61 units in 1 building: 56 homes (1, 2 and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 61 units, 38 are for sale and 23 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
37 units booked out of 38 units for sale (97%).