Ornate Solitaire, Dahisar

by Ornate Dahisar Developers · Dahisar, Mumbai 400068 · Map

Launched
Dec 20224 yrs 10 mths promised
Possession (MahaRERA)
Oct 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
92 of 18151% · 107 rehab units
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale92 booked out of 181 units

Rehab107 units for existing members

Total 288 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
7
2 BHK
29
3 BHK
4
Other units
247
Total units
288
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
181
Rehab units
107

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 34%Dec 2025: Concrete structure (RCC) 55%Jul 2026: Concrete structure (RCC) 91%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 100%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%92
100%91%0%87
100%55%0%73
100%34%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400068

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 10 mths3 yrs 6 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)Oct 2027Jun 2026
Concrete structure (RCC)100%100%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Ornate Solitaire by Ornate Dahisar Developers is a 288-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in December 2022 with possession due in October 2027. 92 units booked out of 181 units for sale. The concrete structure (RCC) is complete.

Read full summary

Ornate Solitaire is a BMC-sanctioned project by Ornate Dahisar Developers in Dahisar, Mumbai 400068, registered with MahaRERA as P51800047937. It was launched in December 2022. It has 288 units in 2 buildings: 41 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 247 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 288 units, 181 are for sale and 107 are rehab units for existing members.

Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.

92 units booked out of 181 units for sale (51%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 91% to 100%.