Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE, Goregaon East

by Raghvendra Construction Company Pvt Ltd · Goregaon East, Mumbai 400063 · Map

Launched
Dec 20223 yrs originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
78%Mid-construction
Booked
91 of 9695%
Buildings
10.3 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
73
2 BHK
23
Total units
96
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)78%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 25%Jul 2026: Concrete structure (RCC) 40%Oct 2026: Concrete structure (RCC) 78%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 78%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%78%0%91
100%40%0%91
100%25%0%58
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400063

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400063
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs4 yrs 6 mths
Possession date extendedBy 1 yr1 of 3
Possession date (MahaRERA)Dec 2026Dec 2027
Concrete structure (RCC)78%93%
Units booked95%75%
MahaRERA complaints (filed by or against the builder)60

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE by Raghvendra Construction Company Pvt Ltd is a 96-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in December 2022 with possession due in December 2026. 91 units booked out of total 96 units. The concrete structure (RCC) is 78% complete.

Read full summary

Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE is an SRA-sanctioned project by Raghvendra Construction Company Pvt Ltd in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800048113. It was launched in December 2022. It has 96 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 78% complete, final finishes not started.

91 units booked out of total 96 units (95%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 40% to 78%.