Vivanta, Goregaon East
by Keyland Developers Private Limited · Goregaon East, Mumbai 400063 · Map
- Launched
- Aug 20236 yrs 4 mths originally promised
- Possession (MahaRERA)
- Jul 2031Extended by 1 yr 7 mths
- Concrete structure
- 0%Early stage
- Booked
- 0 of 990%
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 60
- 2 BHK
- 38
- Other units
- 1
- Total units
- 99
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400063
Projects with 40–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 3 yrs 11 mths |
| Possession date extended | By 1 yr 7 mths | 1 of 3 |
| Possession date (MahaRERA) | Jul 2031 | Dec 2026 |
| Concrete structure (RCC) | 0% | 93% |
| Units booked | 0% | 95% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Navnath Jayas, Goregaon East
- Sheetal Meghdoot, Goregaon East
- Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE, Goregaon East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Navnath Jayas | June 2023 | December 2027 | 100% | 70 units booked out of 73 units for sale |
| Sheetal Meghdoot | January 2023 | December 2026 | 93% | 62 units booked out of 83 units for sale |
| Avant Hillway, Composite Building - B1 Sale Wing, SAPPHIRE | December 2022 | December 2026 | 78% | 91 units booked out of total 96 units |
About this project
Vivanta by Keyland Developers Private Limited is a 99-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in August 2023 with possession due in July 2031. 0 units booked out of total 99 units. Work on the concrete structure (RCC) has not started.
Read full summary
Vivanta is an SRA-sanctioned project by Keyland Developers Private Limited in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800052409. It was launched in August 2023. It has 99 units in 1 building: 98 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2031, extended by 1 year 7 months from the original December 2029. Construction: excavation not started, structure (RCC) not started, final finishes not started.
0 units booked out of total 99 units (0%).