Richmond Ananya, Mulund East
by Divine Enterprises · Mulund East, Mumbai 400081 · Map
- Launched
- Dec 20222 yrs 9 mths originally promised
- Possession (MahaRERA)
- Sep 2026Extended by 1 yr
- Concrete structure
- 86%Mid-construction
- Booked
- 25 of 3866% · 24 in Jul 2026
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 36
- Other units
- 2
- Total units
- 38
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 17
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 86% | 0% | 25 | |
| 100% | 86% | 0% | 24 | |
| 100% | 77% | 0% | 23 | |
| 100% | 18% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400081
Projects with 10–80 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 3 yrs 1 mth |
| Possession date extended | By 1 yr | 2 of 4 |
| Possession date (MahaRERA) | Sep 2026 | Mar 2027 |
| Concrete structure (RCC) | 86% | 100% |
| Units booked | 66% | 91% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Superbia, Mulund East
- Bimal Apartment Chsl, Mulund East
- Jagdale Giriraj, Mulund East
- Om Shankar Bhavan, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Superbia | November 2022 | December 2027 | 20% | 2 units booked out of total 38 units |
| Bimal Apartment Chsl | August 2022 | April 2027 | 100% | 45 units booked out of total 49 units |
| Jagdale Giriraj | May 2022 | January 2027 | 100% | 10 units booked out of 11 units for sale |
| Om Shankar Bhavan | July 2023 | October 2025 | 100% | – |
About this project
Richmond Ananya by Divine Enterprises is a 38-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in December 2022 with possession due in September 2026. 25 units booked out of total 38 units. The concrete structure (RCC) is 86% complete.
Read full summary
Richmond Ananya is an SRA-sanctioned project by Divine Enterprises in Mulund East, Mumbai 400081, registered with MahaRERA as P51800048156. It was launched in December 2022. It has 38 units in 1 building: 36 homes (1 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in September 2026, after an extension of 1 year from the original September 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 86% complete, final finishes not started.
25 units booked out of total 38 units (66%). Since the July 2026 update, 1 more unit has been booked.