Om Shankar Bhavan, Mulund East
Lapsed
by Rebrickers Private Limited · Mulund East, Mumbai 400081 · Map
- Launched
- Jul 20232 yrs 3 mths promised
- Possession (MahaRERA)
- Oct 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 8
- 1 BHK
- 7
- 2 BHK
- 7
- Total units
- 22
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400081
Projects with 10–50 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 3 mths | 2 yrs 9 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Oct 2025 | Mar 2027 |
| Concrete structure (RCC) | 100% | 92% |
| Units booked | – | 66% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Guru Ashish, Mulund East
- Shriram Niwas, Mulund East
- Richmond Ananya, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Guru Ashish | October 2023 | March 2027 | 92% | 6 units booked out of 19 units for sale |
| Shriram Niwas | February 2024 | June 2027 | 100% | 23 units booked out of 26 units for sale |
| Richmond Ananya | December 2022 | September 2026 | 86% | 25 units booked out of total 38 units |
About this project
Om Shankar Bhavan by Rebrickers Private Limited is a 22-unit BMC-sanctioned project in Mulund East, Mumbai 400081, launched in July 2023; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Om Shankar Bhavan is a BMC-sanctioned project by Rebrickers Private Limited in Mulund East, Mumbai 400081, registered with MahaRERA as P51800051913. It was launched in July 2023. It has 22 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in October 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.