Aventus Westbrook, Andheri East

Ready to moveLapsed

by Aventus Infrastructure LLP · Andheri East, Mumbai 400069 · Map

Launched
Jan 20232 yrs 11 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
19 of 2383%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
17
Other units
6
Total units
23
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 75%Dec 2025: Final finishes 98%Jul 2026: Final finishes 98%Oct 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%19
100%100%98%19
100%100%98%19
100%100%75%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aventus Westbrook by Aventus Infrastructure LLP is a 23-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in January 2023; its MahaRERA registration has lapsed. 19 units booked out of total 23 units. The concrete structure (RCC) is complete.

Read full summary

Aventus Westbrook is a BMC-sanctioned project by Aventus Infrastructure LLP in Andheri East, Mumbai 400069, registered with MahaRERA as P51800048625. It was launched in January 2023. It has 23 units in 1 building: 17 homes (3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

19 units booked out of total 23 units (83%).