Orchid Vasundhara, Santacruz West
Ready to move
by Orchid Builtcon Pvt Ltd · Santacruz West, Mumbai 400054 · Map
- Launched
- Jan 20233 yrs 11 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 21 of 3658% · 22 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale21 booked out of 36 units
Rehab22 units for existing members
Land-owner share1 unit, not for sale
Total 59 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 2
- 2 BHK
- 7
- 3 BHK
- 14
- Other units
- 36
- Total units
- 59
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 36
- Rehab units
- 22
- Land-owner share (not for sale)
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 21 | |
| 60% | 5% | 0% | 18 | |
| 60% | 5% | 0% | – | |
| 90% | 8% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400054
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 11 mths | 4 yrs 3 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Dec 2026 | Jun 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 58% | 59% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Fairfield By S Raheja, Santacruz West
- New Saket Co-operative Housing Society Ltd, Santacruz West
- Gateway Residential, Santacruz West
- Redevelopment Of Pearl Palace, Santacruz West
- Shiv Laj, Santacruz West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Fairfield By S Raheja | March 2023 | June 2027 | 0% | 7 units booked out of total 25 units |
| New Saket Co-operative Housing Society Ltd | March 2023 | June 2026 | 100% | 4 units booked out of 12 units for sale |
| Gateway Residential | September 2022 | September 2027 | 100% | 20 units booked out of total 34 units |
| Redevelopment Of Pearl Palace | June 2023 | September 2027 | 100% | 10 units booked out of 12 units for sale |
| Shiv Laj | July 2023 | December 2026 | 100% | 16 units booked out of 18 units for sale |
About this project
Orchid Vasundhara by Orchid Builtcon Pvt Ltd is a 59-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in January 2023 with possession due in December 2026. 21 units booked out of 36 units for sale. The concrete structure (RCC) is complete.
Read full summary
Orchid Vasundhara is a BMC-sanctioned project by Orchid Builtcon Pvt Ltd in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800048969. It was launched in January 2023. It has 59 units in 2 buildings: 23 homes (1, 2 and 3 BHK) and 36 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 59 units, 36 are for sale, 22 are rehab units for existing members and 1 is the land-owner's share, not for sale.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
21 units booked out of 36 units for sale (58%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 5% to 100%.