New Saket Co-operative Housing Society Ltd, Santacruz West

Ready to moveLapsed

by SM Magnate Construction · Santacruz West, Mumbai 400054 · Map

Launched
Mar 20233 yrs 3 mths promised
Possession (MahaRERA)
Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
4 of 1233%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 12 units

Land-owner share12 units, not for sale

Total 24 units. Land-owner units are not for sale.

Project facts

2 BHK
12
3 BHK
12
Total units
24
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
12
Land-owner share (not for sale)
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%4
100%100%95%4
100%100%95%4
100%100%95%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400054

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths4 yrs 1 mth
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2026Mar 2027
Concrete structure (RCC)100%100%
Units booked (free sale)33%59%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

New Saket Co-operative Housing Society Ltd by SM Magnate Construction is a 24-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in March 2023; its MahaRERA registration has lapsed. 4 units booked out of 12 units for sale. The concrete structure (RCC) is complete.

Read full summary

New Saket Co-operative Housing Society Ltd is a BMC-sanctioned project by SM Magnate Construction in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800049992. It was launched in March 2023. It has 24 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 24 units, 12 are for sale and 12 are the land-owner's share, not for sale.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

4 units booked out of 12 units for sale (33%).