Anant Nakshatra, Malad East

by M Construction Company · Malad East, Mumbai 400097 · Map

Launched
Feb 2023First of 2 phases
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
49%Weighted across 2 phases
Booked
–
Buildings
21.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
117
Total units
117
Buildings
2
Land
1.1 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Anant Nakshatra Tower 2
Nearing possession
P5180004933957100%–
Anant Nakshatra Tower 1
Early stage
P51800051692600%–
Show updates by phase

Anant Nakshatra Tower 2 (P51800049339)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%–
100%100%50%–
100%100%50%–
100%57%0%0

"–" means MahaRERA shows no figure for that update.

Anant Nakshatra Tower 1 (P51800051692)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%–
0%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation49%
Concrete structure (slabs)49%
Finishes, lifts and services24%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 49%Dec 2025: Excavation 49%Jul 2026: Excavation 49%Oct 2026: Excavation 49%Dec 2024: Concrete structure (RCC) 28%Dec 2025: Concrete structure (RCC) 49%Jul 2026: Concrete structure (RCC) 49%Oct 2026: Concrete structure (RCC) 49%Dec 2024: Final finishes 0%Dec 2025: Final finishes 24%Jul 2026: Final finishes 24%Oct 2026: Final finishes 24%Excavation 49%Concrete structure (RCC) 49%Final finishes 24%

How to read construction stages

Compared with 5 similar projects in PIN 400097

Projects with 50–250 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 10 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)Dec 2026Jun 2027
Concrete structure (RCC)49%75%
Units booked–67%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Anant Nakshatra by M Construction Company is a 117-unit SRA-sanctioned project in Malad East, Mumbai 400097, registered with MahaRERA in 2 phases, with possession due in December 2026. The concrete structure (RCC) is 49% complete.

Read full summary

Anant Nakshatra is an SRA-sanctioned project by M Construction Company in Malad East, Mumbai 400097, registered with MahaRERA as 2 phases (P51800049339, P51800051692). The first phase was launched in February 2023. Together the phases have 117 units in 2 buildings, with 1 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.

The registered possession date is December 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 49% complete and final finishes 24% complete. Neither phase has its structure complete.