Skip to main content

Redevelopment Of Malad Ajanta Chs, Malad East

by Nareshbhai Vallabhbhai Patel · Malad East, Mumbai 400097 · Map

Launched
Jan 20233 yrs 11 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
40%Mid-construction
Booked (free sale)
67 of 8480% · 60 rehab units
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale67 booked out of 84 units

Rehab60 units for existing members

Total 144 units. Rehab units are not for sale.

Project facts

1 BHK
7
2 BHK
36
3 BHK
13
4 BHK
3
Other units
85
Total units
144
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
84
Rehab units
60

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)40%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 40%Jul 2026: Concrete structure (RCC) 40%Oct 2026: Concrete structure (RCC) 40%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 40%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%40%0%67
100%40%0%67
100%40%0%–
100%40%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400097

Projects with 20–150 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths2 yrs 7 mths
Possession date extendedNo3 of 5
Possession date (MahaRERA)Dec 2026Nov 2026
Concrete structure (RCC)40%100%
Units booked (free sale)80%100%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Redevelopment Of Malad Ajanta Chs by Nareshbhai Vallabhbhai Patel is a 144-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in January 2023 with possession due in December 2026. 67 units booked out of 84 units for sale. The concrete structure (RCC) is 40% complete.

Read full summary

Redevelopment Of Malad Ajanta Chs is a BMC-sanctioned project by Nareshbhai Vallabhbhai Patel in Malad East, Mumbai 400097, registered with MahaRERA as P51800048653. It was launched in January 2023. It has 144 units in 1 building: 59 homes (1, 2, 3 and 4 BHK) and 85 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 144 units, 84 are for sale and 60 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 40% complete, final finishes not started.

67 units booked out of 84 units for sale (80%).