Sach Splendid, Khar West
by Sach Realtors · Khar West, Mumbai 400052 · Map
- Launched
- Feb 20232 yrs 2 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 2 yrs
- Concrete structure
- 60%Mid-construction
- Booked (free sale)
- 7 of 888% · 12 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 8 units
Rehab12 units for existing members
Total 20 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 2
- 3 BHK
- 14
- 4 BHK
- 4
- Total units
- 20
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 8
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 0% | 7 | |
| 100% | 0% | 0% | 7 | |
| 100% | 60% | 0% | 5 | |
| 100% | 60% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400052
Projects with 10–40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 2 mths | 3 yrs 8 mths |
| Possession date extended | By 2 yrs | 1 of 5 |
| Possession date (MahaRERA) | Apr 2027 | Dec 2026 |
| Concrete structure (RCC) | 60% | 100% |
| Units booked (free sale) | 88% | 31% |
| MahaRERA complaints (filed by or against the builder) | 0 | 1 |
The 5 projects
- Platinum Avenue, Khar West
- Khar Hari Niketan, Khar West
- Grace Palacio, Khar West
- Trishaan, Khar West
- K52, Khar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Platinum Avenue | January 2023 | December 2026 | 75% | 23 units booked out of 29 units for sale |
| Khar Hari Niketan | December 2022 | December 2026 | 0% | 4 units booked out of total 13 units |
| Grace Palacio | April 2023 | December 2026 | 100% | 3 units booked out of total 38 units |
| Trishaan | November 2022 | September 2026 | 100% | 3 units booked out of total 27 units |
| K52 | October 2022 | December 2025 | 100% | 14 units booked out of 20 units for sale |
About this project
Sach Splendid by Sach Realtors is a 20-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in February 2023 with possession due in April 2027. 7 units booked out of 8 units for sale. The concrete structure (RCC) is 60% complete.
Read full summary
Sach Splendid is a BMC-sanctioned project by Sach Realtors in Khar West, Mumbai 400052, registered with MahaRERA as P51800049343. It was launched in February 2023. It has 20 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 20 units, 8 are for sale and 12 are rehab units for existing members.
Its registered possession date is April 2027, extended by 2 years from the original April 2025. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.
7 units booked out of 8 units for sale (88%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 60% and the possession date has moved from April 2026 to April 2027.