- Launched
- Oct 20223 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 14 of 2070% · 13 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale14 booked out of 20 units
Rehab13 units for existing members
Total 33 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 20
- 3 BHK
- 6
- 4 BHK
- 7
- Total units
- 33
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 20
- Rehab units
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 14 | |
| 100% | 100% | 80% | 14 | |
| 100% | 100% | 80% | 14 | |
| 100% | 100% | 30% | 3 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400052
Projects with 10–70 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 3 yrs 8 mths |
| Possession date extended | No | 2 of 5 |
| Possession date (MahaRERA) | Dec 2025 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 70% | 24% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 5 projects
- Trishaan, Khar West
- Platinum Avenue, Khar West
- Sach Splendid, Khar West
- Grace Palacio, Khar West
- Atlantis Tower, Khar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Trishaan | November 2022 | September 2026 | 100% | 3 units booked out of total 27 units |
| Platinum Avenue | January 2023 | December 2026 | 75% | 23 units booked out of 29 units for sale |
| Sach Splendid | February 2023 | April 2027 | 60% | 7 units booked out of 8 units for sale |
| Grace Palacio | April 2023 | December 2026 | 100% | 3 units booked out of total 38 units |
| Atlantis Tower | February 2022 | July 2027 | 100% | 4 units booked out of 17 units for sale |
About this project
K52 by Kolte-Patil Developers Limited is a 33-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in October 2022; its MahaRERA registration has lapsed. 14 units booked out of 20 units for sale. The concrete structure (RCC) is complete.
Read full summary
K52 is a BMC-sanctioned project by Kolte-Patil Developers Limited in Khar West, Mumbai 400052, registered with MahaRERA as P51800047424. It was launched in October 2022. It has 33 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 33 units, 20 are for sale and 13 are rehab units for existing members.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
14 units booked out of 20 units for sale (70%).