Skip to main content

Rajshree Fifty Five East, Ghatkopar East

Ready to moveLapsed

by Swaranjali 5 Upgrade LLP · Ghatkopar East, Mumbai 400075 · Map

Launched
Feb 20232 yrs 10 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
81 of 81100% · 30 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale81 booked out of 81 units

Rehab30 units for existing members

Total 111 units. Rehab units are not for sale.

Project facts

1 BHK
47
2 BHK
64
Total units
111
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
81
Rehab units
30

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%81
100%100%95%81
100%100%95%81
100%100%95%79

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400075

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400075
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths3 yrs 9 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2025Dec 2026
Concrete structure (RCC)100%75%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Rajshree Fifty Five East by Swaranjali 5 Upgrade LLP is a 111-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400075, launched in February 2023; its MahaRERA registration has lapsed. 81 units booked out of 81 units for sale. The concrete structure (RCC) is complete.

Read full summary

Rajshree Fifty Five East is a MHADA-sanctioned project by Swaranjali 5 Upgrade LLP in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800049434. It was launched in February 2023. It has 111 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 111 units, 81 are for sale and 30 are rehab units for existing members.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

81 units booked out of 81 units for sale (100%).