Shreenath Enclave, Kandivali West
Ready to moveLapsed
by Shreenathji Infracon Build Pvt Ltd · Kandivali West, Mumbai 400067 · Map
- Launched
- Feb 20232 yrs 9 mths promised
- Possession (MahaRERA)
- Nov 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 9 of 2931%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 15
- 2 BHK
- 2
- 3 BHK
- 1
- 4 BHK
- 1
- Other units
- 10
- Total units
- 29
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 9 | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 85% | 25% | 9 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400067
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 1 yr 10 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Nov 2025 | Dec 2025 |
| Concrete structure (RCC) | 100% | 60% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Kashi Bhuvan, Kandivali West
- Laxmi Heights, Kandivali West
- Muncipal Employees Deep Darshan Co Operative Housing Society Limited, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kashi Bhuvan | February 2023 | September 2025 | 10% | – |
| Laxmi Heights | April 2023 | September 2026 | 60% | 1 unit booked out of total 23 units |
| Muncipal Employees Deep Darshan Co Operative Housing Society Limited | December 2022 | December 2025 | 100% | 15 units booked out of 25 units for sale |
About this project
Shreenath Enclave by Shreenathji Infracon Build Pvt Ltd is a 29-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in February 2023; its MahaRERA registration has lapsed. 9 units booked out of total 29 units. The concrete structure (RCC) is complete.
Read full summary
Shreenath Enclave is a BMC-sanctioned project by Shreenathji Infracon Build Pvt Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800049573. It was launched in February 2023. It has 29 units in 1 building: 19 homes (1, 2, 3 and 4 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in November 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
9 units booked out of total 29 units (31%).