Shraddha Pavillion, Bhandup East

by Shraddha Prime Projects Limited · Bhandup East, Mumbai 400042 · Map

Launched
Feb 20233 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2028Extended by 1 yr 11 mths
Concrete structure
81%Mid-construction
Booked (free sale)
58 of 11451% · 52 rehab units
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale58 booked out of 114 units

Rehab52 units for existing members

Total 166 units. Rehab units are not for sale.

Project facts

1 BHK
70
2 BHK
89
Other units
7
Total units
166
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
114
Rehab units
52

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)81%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 95%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 81%Oct 2026: Concrete structure (RCC) 81%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 81%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%81%0%58
100%81%0%58
100%60%0%48
95%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400042

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400042
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths3 yrs 8 mths
Possession date extendedBy 1 yr 11 mths0 of 3
Possession date (MahaRERA)Dec 2028Dec 2026
Concrete structure (RCC)81%52%
Units booked (free sale)51%31%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Shraddha Pavillion by Shraddha Prime Projects Limited is a 166-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, launched in February 2023 with possession due in December 2028. 58 units booked out of 114 units for sale. The concrete structure (RCC) is 81% complete.

Read full summary

Shraddha Pavillion is a BMC-sanctioned project by Shraddha Prime Projects Limited in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800049739. It was launched in February 2023. It has 166 units in 2 buildings: 159 homes (1 and 2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 166 units, 114 are for sale and 52 are rehab units for existing members.

Its registered possession date is December 2028, extended by 1 year 11 months from the original January 2027. Construction: excavation complete, structure (RCC) 81% complete, final finishes not started.

58 units booked out of 114 units for sale (51%).

Shraddha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA53
Total units across these projects9,707
Completed without extending the possession date16
Completed after an extension4
Lapsed5
Under construction28
Possession date extended on the builder's application18
Typical time from launch to 100% structure4 years
MahaRERA complaints (filed by or against the builder), all Shraddha projects14 (11 of 53 projects)

See all Shraddha projects →