Shraddha Pavillion, Bhandup East
by Shraddha Prime Projects Limited · Bhandup East, Mumbai 400042 · Map
- Launched
- Feb 20233 yrs 11 mths originally promised
- Possession (MahaRERA)
- Dec 2028Extended by 1 yr 11 mths
- Concrete structure
- 81%Mid-construction
- Booked (free sale)
- 58 of 11451% · 52 rehab units
- Buildings
- 20.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale58 booked out of 114 units
Rehab52 units for existing members
Total 166 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 70
- 2 BHK
- 89
- Other units
- 7
- Total units
- 166
- Buildings
- 2
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 114
- Rehab units
- 52
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 81% | 0% | 58 | |
| 100% | 81% | 0% | 58 | |
| 100% | 60% | 0% | 48 | |
| 95% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400042
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 11 mths | 3 yrs 8 mths |
| Possession date extended | By 1 yr 11 mths | 0 of 3 |
| Possession date (MahaRERA) | Dec 2028 | Dec 2026 |
| Concrete structure (RCC) | 81% | 52% |
| Units booked (free sale) | 51% | 31% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Bhagyawan Primrose, Bhandup East
- Bhandup Amol Chs Ltd, Bhandup East
- Krystel By KAMS Realtors, Bhandup East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bhagyawan Primrose | December 2022 | December 2027 | 0% | 31 units booked out of total 187 units |
| Bhandup Amol Chs Ltd | April 2023 | December 2026 | 52% | 36 units booked out of total 116 units |
| Krystel By KAMS Realtors | June 2023 | December 2026 | 95% | 68 units booked out of total 106 units |
About this project
Shraddha Pavillion by Shraddha Prime Projects Limited is a 166-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, launched in February 2023 with possession due in December 2028. 58 units booked out of 114 units for sale. The concrete structure (RCC) is 81% complete.
Read full summary
Shraddha Pavillion is a BMC-sanctioned project by Shraddha Prime Projects Limited in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800049739. It was launched in February 2023. It has 166 units in 2 buildings: 159 homes (1 and 2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 166 units, 114 are for sale and 52 are rehab units for existing members.
Its registered possession date is December 2028, extended by 1 year 11 months from the original January 2027. Construction: excavation complete, structure (RCC) 81% complete, final finishes not started.
58 units booked out of 114 units for sale (51%).
Shraddha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 53 |
|---|---|
| Total units across these projects | 9,707 |
| Completed without extending the possession date | 16 |
| Completed after an extension | 4 |
| Lapsed | 5 |
| Under construction | 28 |
| Possession date extended on the builder's application | 18 |
| Typical time from launch to 100% structure | 4 years |
| MahaRERA complaints (filed by or against the builder), all Shraddha projects | 14 (11 of 53 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.