140 Sher - E- Punjab, Andheri East
Ready to move
by Insha Lifestyle LLP · Andheri East, Mumbai 400093 · Map
- Launched
- Mar 20232 yrs 9 mths originally promised
- Possession (MahaRERA)
- Oct 2027Extended by 1 yr 10 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 9 of 1090% · 8 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 10 units
Rehab8 units for existing members
Total 18 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 7
- 3 BHK
- 8
- Other units
- 3
- Total units
- 18
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 10
- Rehab units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 9 | |
| 100% | 100% | 95% | 9 | |
| 100% | 100% | 95% | 9 | |
| 100% | 90% | 50% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400093
Projects with up to 30 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 4 yrs 2 mths |
| Possession date extended | By 1 yr 10 mths | 0 of 3 |
| Possession date (MahaRERA) | Oct 2027 | Dec 2027 |
| Concrete structure (RCC) | 100% | 60% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Sher E Punjab 02 Guru Sharan, Andheri East
- Gurudarshan, Andheri East
- Om Guru Kripa Co Op Hsg Soc Ltd, Andheri East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sher E Punjab 02 Guru Sharan | March 2023 | March 2026 | 50% | 6 units booked out of 12 units for sale |
| Gurudarshan | August 2023 | March 2028 | 60% | – |
| Om Guru Kripa Co Op Hsg Soc Ltd | October 2023 | December 2027 | 95% | 3 units booked out of total 14 units |
About this project
140 Sher - E- Punjab by Insha Lifestyle LLP is an 18-unit BMC-sanctioned project in Andheri East, Mumbai 400093, launched in March 2023 with possession due in October 2027. 9 units booked out of 10 units for sale. The concrete structure (RCC) is complete.
Read full summary
140 Sher - E- Punjab is a BMC-sanctioned project by Insha Lifestyle LLP in Andheri East, Mumbai 400093, registered with MahaRERA as P51800049852. It was launched in March 2023. It has 18 units in 1 building: 15 homes (2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 10 are for sale and 8 are rehab units for existing members.
Its registered possession date is October 2027, extended by 1 year 10 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
9 units booked out of 10 units for sale (90%).