Gurudarshan, Andheri East
by Balaji Builders And Developers · Andheri East, Mumbai 400093 · Map
- Launched
- Aug 20234 yrs 7 mths promised
- Possession (MahaRERA)
- Mar 2028Not extended
- Concrete structure
- 60%Mid-construction
- Booked
- –
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 4
- 2 BHK
- 4
- Total units
- 8
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 0% | – | |
| 100% | 60% | 0% | – | |
| 100% | 60% | 0% | – | |
| 100% | 60% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400093
Projects with up to 20 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 7 mths | 3 yrs |
| Possession date extended | No | 1 of 3 |
| Possession date (MahaRERA) | Mar 2028 | Oct 2027 |
| Concrete structure (RCC) | 60% | 95% |
| Units booked | – | 50% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Om Guru Kripa Co Op Hsg Soc Ltd, Andheri East
- 140 Sher - E- Punjab, Andheri East
- Sher E Punjab 02 Guru Sharan, Andheri East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Om Guru Kripa Co Op Hsg Soc Ltd | October 2023 | December 2027 | 95% | 3 units booked out of total 14 units |
| 140 Sher - E- Punjab | March 2023 | October 2027 | 100% | 9 units booked out of 10 units for sale |
| Sher E Punjab 02 Guru Sharan | March 2023 | March 2026 | 50% | 6 units booked out of 12 units for sale |
About this project
Gurudarshan by Balaji Builders And Developers is an 8-unit BMC-sanctioned project in Andheri East, Mumbai 400093, launched in August 2023 with possession due in March 2028. The concrete structure (RCC) is 60% complete.
Read full summary
Gurudarshan is a BMC-sanctioned project by Balaji Builders And Developers in Andheri East, Mumbai 400093, registered with MahaRERA as P51800052373. It was launched in August 2023. It has 8 units in 1 building, with 1 RK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.